Dubai Projects Status Tracker

Has your property delivery been delayed? Developers are allowed to delay up to one year after the anticipated completion date in the SPA without any penalty.

Anything after that must be compensated for. So, many investors and homebuyers have asked us for ready properties or homes that are going to be handed over soon.

Check out the below useful tool to follow the status of your construction progress, based on the checks by Dubai Land Department.

Construction progress is a better indicator than an announced handover date for the project completion since most projects are not handed over on time.

  • About to Complete
  • Just Launched
  • Just Completed

Sartoria

Sports City

40% Completed
40% Completed
Launch Jun, 2025
Completion

ELTIERA HEIGHTS

Al Thanyah Fifth

0% Completed
0% Completed
Launch Jun, 2025
Completion

Samana Business Park

Wadi Al Safa 3

0% Completed
0% Completed
Launch Jun, 2025
Completion Sep, 2028

Arch by 7th Key

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion Apr, 2028

Unique One

Dubai South

0% Completed
0% Completed
Launch Jun, 2025
Completion

Rosehill

Dubai Hills Estate

0% Completed
0% Completed
Launch Jun, 2025
Completion Jun, 2029

Eiwan Hights

Sobha Hartland 2

0% Completed
0% Completed
Launch Jun, 2025
Completion Mar, 2028

REGAL CREST

Dubai South

0% Completed
0% Completed
Launch Jun, 2025
Completion Mar, 2027

ALTA VIEW SKYHOMES

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion Jun, 2029

Bay Grove Residences D - Dubai Islands

Dubai Islands

0% Completed
0% Completed
Launch Jun, 2025
Completion Sep, 2028

ARTHOUSE RESIDENCES TOWER A by AVIAAN

Nad Al Shiba First

0% Completed
0% Completed
Launch Jun, 2025
Completion

Flora Bay

Dubai Islands

0% Completed
0% Completed
Launch Jun, 2025
Completion

Floarea Skies

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion Dec, 2028

Celestara Residences

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion May, 2028

TREVINO

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion

DAMAC ISLANDS - SEYCHELLES 2

Al Yelayiss 1

0% Completed
0% Completed
Launch Jun, 2025
Completion Jun, 2029

Pinewood Estate Homes

Me'Aisem First

0% Completed
0% Completed
Launch Jun, 2025
Completion Nov, 2028

Berkeley Square by Prestige One

Jumeirah Village Circle (JVC)

0% Completed
0% Completed
Launch Jun, 2025
Completion

Atelis at d3

Zaabeel Second

0% Completed
0% Completed
Launch Jun, 2025
Completion Aug, 2029

THE CORNER

Wadi Al Safa 5

17% Completed
17% Completed
Launch Jun, 2025
Completion Jun, 2027